15-Minute UPS Backup for a Data Room in Thailand
The Context & Challenge
The data room required backup power for a 180 kW load, with a specified runtime of 15 minutes. The installation also needed a compact layout suited to the available space.
LEOCH Solutions
LEOCH deployed 13 groups of SU192V25 lithium batteries in an integrated UPS backup system. The configuration was designed to deliver the required runtime within a compact installation footprint.
Key Results
The project summary reports 15 minutes of backup for a 180 kW load, meeting the stated runtime requirement. It also describes a small installation footprint and efficient use of space.
-
Client Industry
Data room / IT infrastructure
-
Location:
Thailand
-
Date of Deployment
2020
-
Products Deployed
SU192V25
-
Total Scale
13 Groups